Filling the main basin has now reached completion, which means that the 14-day “stilling test” has begun today, Friday August 9th.  This is the test conducted by C&RT to ensure the basin is water-tight.

Once we have passed the test, the basin entrance will be dug out and final preparations will be done for opening.  The likely opening date is around the end of the month.

We will be supervising towpath moorings outside the marina once the Festival crowds have dispersed.

Please phone or email with any questions!

 

 

 